MANUFACTURING AUTOMATION
Medical
Component Assembly System
Background
Advent Design’s client developed
a new medical diagnostic instrument which included a disposable
reagent vessel preloaded with buffer solutions and stir bars.
Our customer required an automated assembly system to produce
the consumable vessel at a rate of 30 pieces per minute.
System Description


|
Advent designed,
built, and installed two manufacturing systems for the consumable
component of a new medical diagnostic instrument. The first-generation
machine produced a single cavity vessel for the initial
instrument release. The second-generation machine was capable
of producing both the first generation and second generation
vessels, the latter being a four-cavity vessel. The transport
mechanism for the vessels was a multi-vessel based pallet
with a pneumatic walking mechanism which indexed the pallet
vessel to vessel. This allowed an accumulation of 1000+
vessels in a drying oven for an upstream process.
Pallets of 20 vessels were fed into
the system.
- A stir bar was cut and deposited into
the first cavity. The stir bar station was capable of
producing a stir bar as short as .20”.
- Two cavities were sealed with a heat
activated foil cover.
- Two cavities were filled with a buffer
solution. IVEC dispensers were used for liquid handling.
- Foil seals were diecut and thermally
sealed over the last two cavities.
- A sequentially bar coded label was applied
to the top lip of the vessel.
- Barcode label presence was verified,
and barcode sequence validated.
- Individual vessels were ejected from
the pallet, onto an exit conveyor.
Rejects remained in the pallet for operator removal.
- Vessels passed through a metal detector
to detect the presence of the stir bar. Rejects were removed
from the belt.
- The stream of good parts were then counted,
and directed into a pouching machine.
- A pouching machine was included with
the system and packaged 25 vessels to a pouch.
|

Impact
The challenge with the first generation
machine was a very tight implementation schedule. The machine
was designed, built, and acceptance tested in 16 weeks. With the
lessons learned from the first machine, Advent increased the throughput
of the second-generation machine from 30 to 45 vessels per minute.